Around-the-clock dedication at Eliseo Bali Jimbaran!
As of September 30, we successfully executed an extensive night concrete pour for the upper-level floor slab and roof structure. Pouring at night ensures optimal thermal conditions for curing heavy structural concrete in tropical climates. Supported by a continuous stream of Karya Beton mixers and high-reach boom pumps, the team reached major structural heights. Masonry work on the lower levels is also progressing steadily underneath.
Current Progress:
-
Major night concrete pour completed for the upper slab/roof level.
-
Seamless continuous supply chain operation with Karya Beton fleets.
-
Lower-floor concrete block wall masonry well underway.
-
Multi-story bamboo and timber scaffolding systems fully supporting upper forms.
Construction gallery
Up Next:
-
Slab curing and structural inspection.
-
Completion of upper-floor interior and exterior wall masonry.
-
Initial rough-in for electrical, plumbing, and waterproofing systems.